OVERVIEW

Project Description:
Improvements to Ankola-Hubli Road (SH-42) Reach S-7 from Km.75/0 to 132/480
Client name:
Chief Engineer, PWD, Karnataka.
Consultant’s name:
RITES with AHRC Division, Yellapur
Contract value in INR Millions / US$ Mill:
201.21
Completion value INR Millions / US$ Mill:
283.24 / 7.75
Contract Commencement Date:
1-Jan-92
Contract Completion Date:
11-Dec-95
Revised/Expected Completion Date:
20-Feb-96
Name of the Contractor:
Progressive Constructions – Seenaiah & Co. J.V.
JV Partners:
Progressive Constructions Ltd. – B.Seenaiah & Co.
Share in the Joint Venture:
50% – 50%
Key Items in the Contract:
Earthworks
3,64,355 m3
WBM Gr.I, II & III
57,990 m3
Bituminous Macadam
12,533 m3
Dense Bituminous Macadam
40,339 m3
Single Coat Surface Dressing
1,13,870 m2
Tack / Prime Coat
13,35,220 m2
Bridge Details:
Minor Bridges
3
Slab / Pipe Culvets
102 / 12
Temporary Diversion Roads
2 kms
Vertical Improvements/Restructuring
3.255 kms