OVERVIEW

Project Description:
Rehabilitation & Upgradation to 4/6 lane divided carriageway for Package KU-IV from Bhilwara Bypass (Km.120/0 of NH-79) to Chittorgarh (Km.183/0 of NH-79) in the State of Rajasthan
Client name:
National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi.
Consultant’s name:
SNC-Lavalin International Inc.
Contract value in INR Millions / US$ Mill:
1510.40 / 32.03
Completion value INR Millions / US$ Mill:
1774.00 / 38.29
Contract Commencement Date:
28-Nov-01
Contract Completion Date:
16-May-04
Revised/Expected Completion Date:
20-Aug-04
Name of the Contractor:
B.Seenaiah & Company (Projects) Limited
Key Items in the Contract:
Earthworks
19,38,439 m3
GSB
2,32,154 m3
WMM
1,03,373 m3
Prime Coat
3,85,708 m2
Tack Coat
11,48,240 m2
Profile Corrective Course
12,706 m3
DBM
93,448 m3
BC
18,073 m3
Dry Lean Concrete
65,700 m3
Pavement Quality Concrete
1,24,221 m3
Dry Lean Concrete
70,534 m3
Bridge Details:
ROB / RUB
2 nos RoB (2 spans of 18.536 mts and 2 spans 21.989 mtrs with RCC Girders
Flyover
2 spans of 18.536 mts and 2 spans of 21.989 mts RCC girders
Major / Minor Bridges
2 nos 11 spans of 37.0 mtrs each / 11 nos of span 6.60 to 8.80 mtrs
Slab / Pipe Culvets
38 / 44
Drains
7,427 m3
Bored Cast-in-situ piles
653.40 Lm