OVERVIEW

Project Description:
Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0
Length of the Road:
186 Kms
Client name:
Chief Engineer, Roads-II, PWD, Jaipur, Rajasthan, India.
Consultant’s name:
SMEC-ICT, Austrialia
Contract value in INR Millions / US$ Mill:
442.1
Completion value in INR Millions / US$ Mill:
782.90 / 22.30
Contract Commencement Date:
21-Dec-1991
Contract Completion Date:
30-Nov-1995
Revised/Expected Completion Date:
31-May-96
Name of the Contractor:
Progressive Constructions – Seenaiah & Co. J.V.
JV Partners:
Progressive Constructions Ltd. – B.Seenaiah & Co.
Share in the Joint Venture:
50% – 50%
Share in the Joint Venture:
Earthworks
27,67,169 m3
WBM Gr.I, II & III
61,733.90 m3
Bituminous Macadam
1,18,009 m3
Lean Bituminous Macadam
78,121 m3
Dense Bituminous Macadam
18,331 m3
Single Coat Surface Dressing
1,65,977 m2
Tack / Prime Coat
50,13,529 m2
Bridge Details
Major / Minor Bridges
1 / 19
Slab / Pipe Culvets
84 / 26
Bypass at Nasirabad
10.585 kms
Inter Sections / Junctions
31
Temporary Diversion Roads
2 kms
Vertical Improvements/Restructuring
3.255 kms
Horizontal Curves / Realignments
15

* The project was awarded to M/s.B.Seenaiah & Company (Projects) Limited