OnGoing Projects

Construction of Somasila Swarnamukhi Link Canal

OVERVIEW

Project Description: Construction of Somasila Swarnamukhi Link Canal from km.0.000 to km.9.500 including CM & CD works, Investigation, Preparation of Hydraulic Particulars, Designs and Estimation in Nellore District
Client name: Superintending Engineer, S.S.L.C. & S.B. Circle, Dargamitta, Nellore.
Original Contract value in INR Millions: 1026.00
Original Contract value in US$ Millions: 24.98
Contract Commencement Date: 8-May-07
Contract Completion Date: 31-May-10
Work Completed (%): 20.93%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 214.74
Amount of work sub-contracted: NIL
* The project was awarded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%

Package No. 27/2006 : Investigation

OVERVIEW

Project Description: Package No. 27/2006 : Investigation, design and
1. Construction of head regulator in GBR complex and fabrication, erection of gates and hydro mechanical, electrical works and other allied works for head regulator,
2. Excavation of GNSS floow flow canal (Gorakallu Reservoir to OWK Reservoir) for the reach from km.0.000 to km.17.000 and
3. Construction of CM&CD works enroute in Kurnool District
Client name: Superintending Engineer, SRBC Circle No.2, Nandyal, Kurnool.
Original Contract value in INR Millions: 2540.00
Original Contract value in US$ Millions: 57.57
Contract Commencement Date: 19-Feb-07
Contract Completion Date: 30-Nov-10
Work Completed (%): 34.97%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 888.13
Amount of work sub-contracted: NIL
* The project was awarded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%

Investigation, Design, Estimation and construction of Barrage across Champavathi river

OVERVIEW

Project Description: Investigation, Design, Estimation and construction of Barrage across Champavathi river with afflux bunds, head sluice, excavation of diversion canal including CM & CD works and tunnel, formation of earth dam to form a reservoir with two head sluices, surplus weir, surplus course and protection bunds, excavation of right and left main canal with distributory system with CM & CD works Tarakarama Thirtha Sagaram Reservoir Project
Client name: Superintending Engineer, TTPR Circle, Vizianagaram-3.
Original Contract value in INR Millions: 1815.00
Original Contract value in US$ Millions: 39.87
Contract Commencement Date: 24-May-06
Revised/Expected Completion Date: EOT Submitted
Contract Completion Date: 31-Dec-10
Work Completed (%): 20.57%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 373.42
Amount of work sub-contracted: NIL
* The project was awarded to M/s.CR18G-BSCPL JV. Our Share in the Joint Venture is 50%

Veligonda Project – Closing of Kakarla Gap

OVERVIEW

Project Description: Veligonda Project – Closing of Kakarla Gap by Constructing a N.O.F. Dam excavation of Link Canal and Part of Eastern Canal together with distributory system including construction of CM & CD Works
Client name: Project Administrator & Superintending Engineer, Veligonda Project Circle, Ongole.
Original Contract value in INR Millions: 4591.90
Original Contract value in US$ Millions: 105.34
Contract Commencement Date: 22-Aug-05
Contract Completion Date: 31-Aug-10
Work Completed (%): 29.41%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 1350.44
Amount of work sub-contracted: NIL
* The project was awarded to M/s.SCL-BSCPL JV. Our Share in the Joint Venture is 35%