OnGoing Projects
Two-laning of Muzaffarpur
Sonbarsa Section of NH -77 (from km 2.8 to km 89.00 ) in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis
OVERVIEW
Project Description: | Two-laning of Muzaffarpur – Sonbarsa Section of NH -77 (from km 2.8 to km 89.00 ) in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis |
Original Contract value in INR Millions: | 5700.00 |
Original Contract value in US$ Millions: | 122.08 |
Work Completed (%): | 0% |
Certified amount – Actual workdone Amount (Rs. Millions) as on date: | 0.00 |
Amount of work sub-contracted: | NIL |
Mokama-Munger Highway
Two laning with paved shoulders of Mokama Munger section of NH-80 from km 1.430 to km 70.00 in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis
OVERVIEW
Project Description: | Two laning with paved shoulders of Mokama Munger section of NH-80 from km 1.430 to km 70.00 in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis |
Client name: | Mokama Munger Highway Limited |
Original Contract value in INR Millions: | 3900.00 |
Original Contract value in US$ Millions: | 84.78 |
Work Completed (%): | 0.00 |
Certified amount – Actual work done Amount (Rs. Millions) as on date: | 0% |
Amount of work sub-contracted: | NIL |
Four laning of Devihalli-Hassan
Deveihalli-Hassan section from Km.110.000 to km.189.500 of NH-48 including a new 2-lane
OVERVIEW
Project Description: | Four laning of Deveihalli-Hassan section from Km.110.000 to km.189.500 of NH-48 including a new 2-lane with paved shoulders bypass for channarayapatna town and widening of existing Hassan bypass to 2-lane with paved shoulders on DBFOT basis in the state of Karnataka under NHDP phase III A |
Client name: | Larsen & Turbo Limited |
Original Contract value in INR Millions: | 3429.20 |
Original Contract value in US$ Millions: | 74.14 |
Work Completed (%): | 0% |
Certified amount – Actual workdone Amount (Rs. Millions) as on date: | 0.00 |
Amount of work sub-contracted: | NIL |
Four laning of Godhra to Gujarat
Border Section of NH 59 from Km 129.300 to Km 215.900
OVERVIEW
Project Description: | Four laning of Godhra to Gujarat/Madhya Pradesh Border Section of NH 59 from Km 129.300 to Km 215.900 in the State of Gujarat on Design Build, Finance, Operate and Transfer (DBFOT) under NHDP III Project |
Client name: | BSCPL Godhra Tollways Limited |
Original Contract value in INR Millions: | 6550.00 |
Original Contract value in US$ Millions: | 140.41 |
Work Completed (%): | 0% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 0.00 |
Amount of work sub-contracted: | NIL |
Six laning of Chilkaluripet
Nellore section of NH-5 from km 1182.802 to km 1366.547(approx. length- 183.620 km)
OVERVIEW
Project Description: | Six laning of Chilkaluripet – Nellore section of NH-5 from km 1182.802 to km 1366.547(approx. length- 183.620 km) in the State of Andhra Pradesh under NHDP Phase V to be executed as BOT (Toll) project on DBFOT Pattern |
Client name: | Simhapuri Expressway Limited |
Original Contract value in INR Millions: | 21500.00 |
Original Contract value in US$ Millions: | 467.39 |
Work Completed (%): | 0% |
Certified amount – Actual workdone Amount (Rs. Millions) as on date: | 0.00 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Kursela-Pothia-Falka-Meergunj-Sarsi-Kalabalua-Ranigunj-Shaifgunj-Forbesgunj
OVERVIEW
Project Description: | Development of Road Kursela-Pothia-Falka-Meergunj-Sarsi-Kalabalua-Ranigunj-Shaifgunj-Forbesganj – Pkg.9 |
Client name: | Road Construction Department, Govt. of Bihar |
Original Contract value in INR Millions: | 2779.26 |
Original Contract value in US$ Millions: | 55.06 |
Contract Commencement Date: | 02-Jan-08 |
Contract Completion Date: | 31-Jan-11 |
Work Completed (%) | 53% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 1579.54 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Araria-Ranigunj-Jarhia-Trivenigunj-Pipra-Supaul-Bishunpur-Bhaptiyahi
OVERVIEW
Project Description: | Development of Road Araria-Ranigunj-Jarhia-Trivenigunj-Pipra-Supaul-Bishunpur-Bhaptiyahi – Pkg.8 |
Client name: | Road Construction Department, Govt. of Bihar |
Original Contract value in INR Millions: | 2997.55 |
Original Contract value in US$ Millions: | 59.39 |
Contract Commencement Date: | 03-Jun-09 |
Contract Completion Date: | 31-Jul-11 |
Work Completed (%) | 48% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 1452.55 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Construction of Afghan Parliament and Indian Chancery Buildings at Kabul, Afghanisthan
OVERVIEW
Project Description: | Construction of Afghan Parliament and Indian Chancery Buildings at Kabul, Afghanisthan |
Client name: | Central Public Works Department, Govt. of India. |
Original Contract value in INR Millions: | 6220.26 |
Original Contract value in US$ Millions: | 126.94 |
Contract Commencement Date: | 25-Jan-09 |
Contract Completion Date: | 31-Jan-12 |
Revised/Expected Completion Date: | 31-Jan-12 |
Work Completed (%) | 18% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 1132.75 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Construction of the Ghazni- Gardez and Gardez – Khost Roads in Afghanistan.
OVERVIEW
Project Description: | Construction of the Ghazni- Gardez and Gardez – Khost Roads in Afghanistan. |
Client name: | The Louis Berger Group – Black and Veatch JV Afghanistan. |
Original Contract value in INR Millions: | 4212.04 |
Original Contract value in US$ Millions: | 85.96 |
Contract Commencement Date: | 20-Apr-08 |
Contract Completion Date: | 31-Dec-10 |
Work Completed (%) | 49.05% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 2065.85 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Construction of New Four Lane Roads (Road Nos.2,7,9A,10 &11) in Naya Raipur Development Area in the State of Chhattisgarh
OVERVIEW
Project Description: | Construction of New Four Lane Roads (Road Nos.2,7,9A,10 &11) in Naya Raipur Development Area in the State of Chhattisgarh. |
Client name: | Naya Raipur Development Authority, Govt. of Chhattisgarh. |
Consultant's name: | M/s.Sheladia Associates Inc in association with Vax Consultants Pvt. Ltd. |
Original Contract value in INR Millions: | 1449.69 |
Original Contract value in US$ Millions: | 36.87 |
Contract Commencement Date: | 02-Jan-08 |
Contract Completion Date: | 31-Oct-10 |
Work Completed (%) | 83.39% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 1208.93 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.37.75 to Km 0.00 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-9.
OVERVIEW
Project Description: | Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.37.75 to Km 0.00 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-9. |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Scott Wilson India (P) Ltd., Rajkumar Ganj, Darbhanga, 846 004 (Bihar). |
Original Contract value in INR Millions: | 3230.02 |
Original Contract value in US$ Millions: | 71.36 |
Contract Commencement Date: | 28-Jan-06 |
Contract Completion Date: | 31-Dec-10 |
Revised/Expected Completion Date: | 31-Dec-10 |
Work Completed (%) | 98.47% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 3180.59 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.69.80 to Km 37.75 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-8.
OVERVIEW
Project Description: | Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.69.80 to Km 37.75 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-8. |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Scott Wilson India (P) Ltd., Rajkumar Ganj, Darbhanga, 846 004 (Bihar). |
Original Contract value in INR Millions: | 3603.00 |
Original Contract value in US$ Millions: | 79.60 |
Contract Commencement Date: | 28-Jan-06 |
Contract Completion Date: | 31-Dec-10 |
Revised/Expected Completion Date: | 31-Dec-10 |
Work Completed (%) | 96.27% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 3468.55 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Widening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from Km.155.00 (Kosi Western Ring Bund) to Km.110.00 (Jhanjharpur) in the State of Bihar on Eats West Corridor under NHDP-Phase-II, Project No.C-II/BR-6
OVERVIEW
Project Description: | Widening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from Km.155.00 (Kosi Western Ring Bund) to Km.110.00 (Jhanjharpur) in the State of Bihar on East West Corridor under NHDP-Phase-II, Project No.C-II/BR-6 |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Wilbur Smith Associates Pvt. Ltd., 75, 14th Cross 2nd Floor, 1st Block, RT Nagar, Bangalore, Karnataka. |
Original Contract value in INR Millions: | 3834.23 |
Original Contract value in US$ Millions: | 87.17 |
Contract Commencement Date: | 28-Jan-06 |
Contract Completion Date: | 30-Nov-10 |
Revised/Expected Completion Date: | 30-Nov-10 |
Work Completed (%) | 93.39% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 3580.78 |
Amount of work sub-contracted: | NIL |
DEVELOPMENT OF ROAD
Lucknow Muzaffar National Highway Project on NH-28 – Package No.LMNHP-EW-II-WB-6
OVERVIEW
Project Description: | Lucknow Muzaffar National Highway Project on NH-28 – Package No.LMNHP-EW-II-WB-6 |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | ROUGHTON INTERNATIONAL JV CES GROUP, C-188/63, Kasya Road, Padleyganj, Gorakhpur – 273 009, Uttar Pradesh. |
Original Contract value in INR Millions: | 2743.81 |
Original Contract value in US$ Millions: | 62.97 |
Contract Commencement Date: | 24-Oct-05 |
Contract Completion Date: | 31-Oct-10 |
Revised/Expected Completion Date: | 31-Oct-10 |
Work Completed (%) | 89.37% |
Certified amount - Actual workdone Amount (Rs. Millions) as on date: | 2452.20 |
Amount of work sub-contracted: | NIL |
Completed Projects
DEVELOPMENT OF ROAD
Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0
OVERVIEW
Project Description: | Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0 |
Length of the Road: | 186 Kms |
Client name: | Chief Engineer, Roads-II, PWD, Jaipur, Rajasthan, India |
Consultant's Name: | SMEC-ICT, Austrialia |
Contract value in INR Millions / US$ Mill: | 442.1 |
Completion value in INR Millions / US$ Mill: | 782.90 / 22.30 |
Contract Commencement Date: | 21-Dec-1991 |
Contract Completion Date: | 30-Nov-1995 |
Revised/Expected Completion Date: | 31-May-96 |
Name of the Contractor: | Progressive Constructions – Seenaiah & Co. J.V. |
JV Partners: | Progressive Constructions Ltd. – B.Seenaiah & Co. |
Share in the Joint Venture: | 50% – 50% |
Share in the Joint Venture: | Earthworks - 27,67,169 m3 WBM Gr.I, II & III - 61,733.90 m3 Bituminous Macadam - 1,18,009 m3 Lean Bituminous Macadam - 78,121 m3 Dense Bituminous Macadam - 18,331 m3 Single Coat Surface Dressing - 1,65,977 m2 Tack / Prime Coat - 50,13,529 m2 |
Bridge Details | Major / Minor Bridges - 1 / 19 Slab / Pipe Culvets - 84 / 26 Bypass at Nasirabad - 10.585 kms Inter Sections / Junctions - 31 Temporary Diversion Roads - 2 kms Vertical Improvements/Restructuring - 3.255 kms Horizontal Curves / Realignments - 15 |
DEVELOPMENT OF ROAD
Four Laning of Nagda to Simlada – Dosi / Sejawata from km.25.00 to km. 100.00 on SH-31 Section in the State of Madhya Pradesh
OVERVIEW
Project Description: | Four Laning of Nagda to Simlada – Dosi / Sejawata from km.25.00 to km. 100.00 on SH-31 Section in the State of Madhya Pradesh |
Client name: | Pan India Infrastructures Private Limited. |
Contract value in INR Millions / US$ Mill: | 3800.00 / 95.05 |
Completion value in INR Millions / US$ Mill: | 3435.50 / 73.52 |
Contract Commencement Date: | 01-Apr-08 |
Contract Completion Date: | 30-Dec-09 |
Name of the Contractor: | BSCPL Infrastructure Limited |
JV Partners: | Progressive Constructions Ltd. – B.Seenaiah & Co. |
Share in the Joint Venture: | 100% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 32,23,524 m3 GSB - 4,41,218 m3 WMM - 3,58,263 m3 Prime Coat - 13,27,612 m2 Tack Coat - 14,77,004 m2 DBM - 1,60,127 m3 BC - 55,074 m3 DLC - 1,542 m3 PQC - 2,926 m3 Plain Cement Concrete - 42,184 m3 Reinforced Cement Concrete - 30,132 m3 Reinforcement - 2,808 Mt |
DEVELOPMENT OF ROAD
Four laning of Jhansi-Lakhnadon section km.255 to km 297 of NH-26 in the state of Madhya Pradesh
OVERVIEW
Project Description: | Four laning of Jhansi-Lakhnadon section km.255 to km 297 of NH-26 in the state of Madhya Pradesh |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Contract value in INR Millions / US$ Mill: | 1896.30 / 41.35 |
Completion value in INR Millions / US$ Mill: | 2065.90 / 44.48 |
Contract Commencement Date: | 27-May-06 |
Contract Completion Date: | 05-Dec-09 |
Name of the Contractor: | BSCPL Infrastructure Limited |
Share in the Joint Venture: | 100% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 35,64,850 m3 GSB - 2,53,985 m3 WMM - 2,13,007 m3 Prime Coat - 8,20,189 m2 Tack Coat - 21,49,884 m2 DBM - 62,037 m3 BM - 59,877 m3 BC - 28,075 m3 Mix Seal Surfacing Course - 88,768 m2 Plain Cement Concrete - 35,004 m3 Reinforced Cement Concrete - 33,686 m3 Pile Foundation 1200mm dia - 33,686 m3 Reinforcement - 3937 Mt Well Foundation - 339 Lm |
DEVELOPMENT OF ROAD
Widening/modification of roads to create multiple lanes of existing carriageway for high capacity bus system in Delhi – Section: Ambedkar Nagar to Delhi Gate
OVERVIEW
Project Description: | Construction works related to widening/modification of roads to create multiple lanes of existing carriageway for high capacity bus system in Delhi – Section: Ambedkar Nagar to Delhi Gate |
Client name: | Commissioner, Delhi Municipal Corporation, New Delhi. |
Contract value in INR Millions / US$ Mill: | 1290.78 / 27.93 |
Completion value in INR Millions / US$ Mill: | 1216.48 / 26.29 |
Contract Commencement Date: | 05-Sep-06 |
Contract Completion Date: | 26-Nov-09 |
Name of the Contractor: | BSC-C&C Joint Venture |
Share in the Joint Venture: | 50% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 30,866 m3 GSB - 21,082 m3 WMM - 15,736 m3 Prime Coat - 61,452 m2 Tack Coat - 7,66,068 m2 DBM - 59,332 m3 BM - 12,220 m3 BC - 14,194 m3 Mastic Asphalt - 1,72,982 m2 PQC - 27,278 m3 DLC - 4,795 m3 Plain Cement Concrete - 8,382 m3 Reinforcement - 415 Mt |
DEVELOPMENT OF ROAD
Four laning from km.551.00 to km.526.00 of Siliguri to Islampur section of NH-31 in West Bengal
OVERVIEW
Project Description: | 4-laning from km.551.00 to km.526.00 of Siliguri to Islampur section of NH-31 in West Bengal |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Contract value in INR Millions / US$ Mill: | 1588.94 / 35.83 |
Completion value in INR Millions / US$ Mill: | 2149.41 / 45.28 |
Contract Commencement Date: | 05-Apr-06 |
Contract Completion Date: | 05-Apr-06 |
Name of the Contractor: | BSCPL Infrastructure Limited |
Share in the Joint Venture: | 100% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 9,37,053 m3 GSB - 1,29,888 m3 WMM - 84,005 m3 Prime Coat - 3,20,729 m2 Tack Coat - 12,27,340 m2 BM - 26,003 m3 DBM - 34,258 m3 BC - 34,258 m3 SDBC - 4,342 m3 PQC - 65,678 m3 DLC - 34,243 m3 Plain Cement Concrete - 35,085 m3 Reinforced Cement Concrete - 28,958 m3 Reinforcement - 3,157 Mt Pile Foundation 1200mm dia - 240 Lm Pile Foundation 1200mm dia - 231 Lm |
DEVELOPMENT OF ROAD
Rehabilitation and Upgradation of Bekaria-Gogunda Section (Km.29.00 to Km.73.00) of NH-76 to 4 lane divided carriageway configuration in the state of Rajasthan on East West Corridors [Contract Package No.EW-II (RJ-2)]
OVERVIEW
Project Description: | Rehabilitation and Upgradation of Bekaria-Gogunda Section (Km.29.00 to Km.73.00) of NH-76 to 4 lane divided carriageway configuration in the state of Rajasthan on East West Corridors [Contract Package No.EW-II (RJ-2)] |
Client name: | National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi. |
Contract value in INR Millions / US$ Mill: | 4115.00 / 89.47 |
Completion value in INR Millions / US$ Mill: | 4850.50 / 95.62 |
Contract Commencement Date: | 6-Nov-05 |
Contract Completion Date: | 28-Feb-07 |
Name of the Contractor: | SOMA – BSCPL JV. |
Share in the Joint Venture: | 50% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 101,80,581 m3 GSB - 1,99,554 m3 WMM - 2,03,761 m3 WMM - 7,58,778 m2 Prime Coat - 17,39,820 m2 DBM - 90,954 m3 BC - 31,394 m3 Concrete - 1,97,358 m3 Tunnel Excavation - 1,03,743 m3 |
DEVELOPMENT OF ROAD
Upgrading of Roads from Arcot to Ulundurpettai (Elvanasur), Polur to Chengam, Vriddhachalam to Tiruvarur, Jayankondam to Ariyalur and New Bypass Roads at Chidambaram, Sirkazhi, Arani, Polur, Tiruvannamalai, Tirukkovilur, Vriddhachalam, Ariyalur and Tiruvar
OVERVIEW
Project Description: | Upgrading of Roads from Arcot to Ulundurpettai (Elvanasur), Polur to Chengam, Vriddhachalam to Tiruvarur, Jayankondam to Ariyalur and New Bypass Roads at Chidambaram, Sirkazhi, Arani, Polur, Tiruvannamalai, Tirukkovilur, Vriddhachalam, Ariyalur and Tiruvar |
Client name: | Project Director, Tamil Nadu Road Development Corporation, Chennai |
Contract value in INR Millions / US$ Mill: | 1689.63 / 37.76 |
Completion value in INR Millions / US$ Mill: | 2082.53 / 46.92 |
Contract Commencement Date: | 30-Nov-04 |
Contract Completion Date: | 15-Jun-09 |
Name of the Contractor: | KMC – OSE – BSCPL J.V. |
Share in the Joint Venture: | 331/3% – 331/3% – 331/3% |
Key Items in the Contract: | Earthwork Excv. & Embankment - 11,18,354 m3 GSB - 4,75,653 m3 WMM - 2,68,758 m3 Prime Coat - 9,04,300 m2 Tack Coat - 22,45,614 m2 DBM - 1,23,598 m3 BC - 40,297 m3 Plain Cement Concrete - 32,863 m3 Reinforced Cement Concrete - 2,319 m3 Prestressed Concrete - 1,518 m3 Pile Foundation 750mm dia - 1,636 Lm Pile Foundation 900mm dia - 779 Lm Open Drains - 10,730 Lm Saucer Drains - 8,597 Lm Reinforcement - 621 Mt |
DEVELOPMENT OF ROAD
Rehabilitation of Taloqan-Kishem Road
OVERVIEW
Project Description: | Rehabilitation of Taloqan-Kishem Road |
Client name: | Ministry of Public Works, Islamic Republic of Afghanisthan, Afghanisthan. |
Consultant’s name: | SMEC |
Contract value in US$ Mill: | 22.41 |
Completion value in US$ Mill: | 27.83 |
Contract Commencement Date: | 1-Feb-06 |
Contract Completion Date: | 19-Dec-07 |
Name of the Contractor: | BSC-C&C JOINT VENTURE |
Share in the Joint Venture: | 50% – 50% |
DEVELOPMENT OF ROAD
Reconstruction of Jalalabad to Asmar Road Km.0+000 to Km.121+500
OVERVIEW
Project Description: | Reconstruction of Jalalabad to Asmar Road Km.0+000 to Km.121+500 |
Client name: | United Nations Office for Project Services ( UNOPS) / United States Agency for International Development, Kabul, Afghanistan. |
Consultant's Name: | Louis Berger Group Inc., USA |
Contract value in US$ Mill: | 40.65 |
Completion value in US$ Mill: | 39.42 |
Contract Commencement Date: | 1-Nov-05 |
Contract Completion Date: | 4-Apr-07 |
Name of the Contractor: | BSC-C&C JOINT VENTURE. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 2,34,909 m3 GSB - 1,49,105 m3 WMM - 1,53,214 m3 Prime Coat - 8,78,891 m2 DBST - 17,57,460 m2 |
Bridge Details | Bridges - 10 Box / Pipe Culvets - 159 / 431 Causeways - 52 Drains - 13521 mtrs |
DEVELOPMENT OF ROAD
Rehablitation of Economic Facilities & Services REFS Program – Kandahar to Heart Highway Improvement Project – Phase II, Package V – Renovation and Reconstruction Km 456+000 to Km 557+462
OVERVIEW
Project Description: | Rehabilitation of Economic Facilities & Services REFS Program – Kandahar to Heart Highway Improvement Project – Phase II, Package V – Renovation and Reconstruction Km 456+000 to Km 557+462 |
Client name: | United States Agency for International Development, Kabul, Afghanistan. |
Consultant's Name: | Louis Berger Group Inc., USA |
Contract value in US$ Mill: | 40.96 |
Completion value in US$ Mill: | 51.31 |
Contract Commencement Date: | 6-Oct-04 |
Contract Completion Date: | 23-Oct-06 |
Name of the Contractor: | BSC-C&C JOINT VENTURE. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 14,47,424 m3 GSB - 2,76,501 m3 WMM - 1,50,826 m3 BM - 2,72,217 Mt BC - 79,293 Mt SBST - 54,469 m2 Milling / Rubblization - 54,469 m2 |
Bridge Details | Major / Minor Bridges - 2 nos 70.50 mtrs & 408.90 mtrs / 8 nos Slab / Pipe Culvets - 31 / 197 |
DEVELOPMENT OF ROAD
Rehablitation of Economic Facilities & Services REFS Program – Design-Build, Contract for the Rehabilitation of the “Section E” (85 Km stretch from Km.262 to Km.347) of Kabul-Kandahar Highway
OVERVIEW
Project Description: | Rehablitation of Economic Facilities & Services REFS Program – Design-Build, Contract for the Rehabilitation of the “Section E” (85 Km stretch from Km.262 to Km.347) of Kabul-Kandahar Highway |
Client name: | United States Agency for International Development, Kabul, Afghanistan. |
Consultant's Name: | Louis Berger Group Inc., USAd. |
Contract value in US$ Mill: | 39.93 |
Completion value US$ Mill: | 44.19 |
Contract Commencement Date: | 31-May-03 |
Contract Completion Date: | 26-Jun-05 |
Name of the Contractor: | BSC-C&C JOINT VENTURE. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 14,47,424 m3 GSB - 2,76,501 m3 WMM - 1,50,826 m3 BM - 2,72,217 Mt BC - 79,293 Mt SBST - 54,469 m2 |
Bridge Details | Major / Minor Bridges - 16 nos with total length of 768 mts Slab / Pipe Culvets - 338 Causeways - 3 nos |
DEVELOPMENT OF ROAD
Design-Build Contract for the Rehabilitation of Kandahar to Spin Boldak Road (Section Km.0+163 to Km.61+440 and from Km.89+771 to Km.90+611)
OVERVIEW
Project Description: | Design-Build Contract for the Rehabilitation of Kandahar to Spin Boldak Road (Section Km.0+163 to Km.61+440 and from Km.89+771 to Km.90+611) |
Client name: | Ministry of Public Works, Islamic Republic of Afghanisthan, Afghanisthan. |
Consultant's Name: | Sheladia Associates Inc., USA |
Contract value in US$ Mill: | 24.17 |
Completion value US$ Mill: | 23.34 |
Contract Commencement Date: | 15-May-03 |
Contract Completion Date: | 26-Nov-05 |
Name of the Contractor: | BSC-C&C JOINT VENTURE. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 10,96,655 m3 GSB - 1,23,007 m3 WMM - 36,053 m3 Prime Coat - 2,02,390 m2 Tack Coat - 7,37,758 m2 DBM - 23,684 m3 BC - 9,228 m2 |
Bridge Details | Major / Minor Bridges - 3 bridges of 316.65 mts, 190 mts & 280 mtrs Slab / Pipe Culvets - 136 Drains - 8,099 mts Causeways - 1,057 mts |
DEVELOPMENT OF ROAD
Four laning of Satara Kolhapur upto Maharashtra State Border Section of NH-4 Phase – I (Km 592.240 to Km.616.000)
OVERVIEW
Project Description: | Four laning of Satara Kolhapur upto Maharashtra State Border Section of NH-4 Phase – I (Km 592.240 to Km.616.000) |
Client name: | Maharashtra State Road Development Corporation Ltd. |
Consultant's Name: | CES (India) Pvt. Ltd. |
Contract value in US$ Mill: | 787.67 / 16.32 |
Completion value US$ Mill: | 889.10 / 19.67 |
Contract Commencement Date: | 3-May-02 |
Contract Completion Date: | 31-Dec-05 |
Revised/Expected Completion Date: | 31-Dec-05 |
Name of the Contractor: | BSCPL-SCL JOINT VENTURE. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 10,96,655 m3 GSB - 1,23,007 m3 WMM - 36,053 m3, Prime Coat - 2,02,390 m2 Tack Coat - 7,37,758 m2 BM - 11,409 m3 DBM + PCC - 23,684 m3 BC - 9,228 m2 Dry Lean Concrete - 26,691 m3 Pavement Quality Concrete - 53,250 m3 Cement Concrete Kerb - 4,186 m3 |
Bridge Details | Major / Minor Bridges - 1 bridge 7 spans of 20.7 mtrs each – length 148 mtrs |
DEVELOPMENT OF ROAD
Widening & strengthening of existing 2-lane carriageway of NH-60 from Laxmannath (Km.53.410) to Kharagpur (Km.119.275) in state of West Bengal, India
OVERVIEW
Project Description: | Widening & strengthening of existing 2-lane carriageway of NH-60 from Laxmannath (Km.53.410) to Kharagpur (Km.119.275) in state of West Bengal, India |
Client name: | National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Louis Berger International Inc. |
Contract value in INR Millions / US$ Mill: | 3293.29 / 70.17 |
Completion value INR Millions / US$ Mill: | 3419.94 / 74.68 |
Contract Commencement Date: | 30-May-01 |
Contract Completion Date: | 29-Feb-04 |
Revised/Expected Completion Date: | 25-May-06 |
Name of the Contractor: | B.Seenaiah & Company (Projects) Limited. |
Key Items in the Contract: | Earthworks - 73,39,893 m3 GSB - 3,37,877 m3 WMM - 18,066 m3 Prime Coat - 82,090 m2 Tack Coat - 1,36,345 m2 BC - 2,07,719 m2 Dry Lean Concrete - 1,89769 m3 Pavement Quality Concrete - 1,89769 m3 Bituminous Mastic Course - 1,89769 m3 |
Bridge Details | Flyover - 2 Major / Minor Bridges - 1 / 7 Drains - 11,404 Lm |
DEVELOPMENT OF ROAD
Widening of existing 2-lanes to 6-lanes divided carriageway facility including rehabilitation of existing 2-lanes from km.273.500 to km.363.885 on Jaipur-Kishangarh section of NH-8 in Rajasthan
OVERVIEW
Project Description: | Widening of existing 2-lanes to 6-lanes divided carriageway facility including rehabilitation of existing 2-lanes from km.273.500 to km.363.885 on Jaipur-Kishangarh section of NH-8 in Rajasthan |
Client name: | GVK Jaipur-Kishangarh Expressway Limited. |
Consultant's Name: | Lea Associates South Asia Pvt. Ltd. |
Contract value in INR Millions / US$ Mill: | 2389.80 / 50.12 |
Completion value INR Millions / US$ Mill: | 2389.80 / 54.63 |
Contract Commencement Date: | 28-Mar-03 |
Contract Completion Date: | 27-Mar-05 |
Revised/Expected Completion Date: | 27-Mar-05 |
Name of the Contractor: | B.Seenaiah & Company (Projects) Limited. |
Key Items in the Contract: | Earthworks - 21,92,816 m3 GSB - 3,75,000 m3 WMM - 3,27,430 m3 Prime Coat - 11,54,556 m2 Tack Coat - 43,71,629 m2 BM - 89,973 m3 DBM - 1,33,188 m3 BC - 68,028 m3 Dry Lean Concrete - 17,834 m3 |
Bridge Details | Flyover - 2 Major / Minor Bridges - 1 / 7 |
DEVELOPMENT OF ROAD
Rehabilitation & Upgradation to 4/6 lane divided carriageway for Package KU-IV from Bhilwara Bypass (Km.120/0 of NH-79) to Chittorgarh (Km.183/0 of NH-79) in the State of Rajasthan
OVERVIEW
Project Description: | Rehabilitation & Upgradation to 4/6 lane divided carriageway for Package KU-IV from Bhilwara Bypass (Km.120/0 of NH-79) to Chittorgarh (Km.183/0 of NH-79) in the State of Rajasthan |
Client name: | National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | SNC-Lavalin International Inc. |
Contract value in INR Millions / US$ Mill: | 1510.40 / 32.03 |
Completion value INR Millions / US$ Mill: | 1774.00 / 38.29 |
Contract Commencement Date: | 28-Nov-01 |
Contract Completion Date: | 16-May-04 |
Revised/Expected Completion Date: | 20-Aug-04 |
Name of the Contractor: | B.Seenaiah & Company (Projects) Limited |
Key Items in the Contract: | Earthworks - 19,38,439 m3 GSB - 2,32,154 m3 WMM - 1,03,373 m3 Prime Coat - 3,85,708 m2 Tack Coat - 11,48,240 m2 Profile Corrective Course - 12,706 m3 DBM - 93,448 m3 BC - 18,073 m3 Dry Lean Concrete - 65,700 m3 Pavement Quality Concrete - 1,24,221 m3 Dry Lean Concrete - 70,534 m3 |
Bridge Details | ROB / RUB - 2 nos RoB (2 spans of 18.536 mts and 2 spans 21.989 mtrs with RCC Girders Flyover - 2 spans of 18.536 mts and 2 spans of 21.989 mts RCC girders Major / Minor Bridges - 2 nos 11 spans of 37.0 mtrs each / 11 nos of span 6.60 to 8.80 mtrs Slab / Pipe Culvets - 38 / 44 Drains - 7,427 m3 Bored Cast-in-situ piles - 653.40 Lm |
DEVELOPMENT OF ROAD
Four laning including strengthening of existing two lane pavement from Barwa Adda to Barakar in the State of Bihar (Jharkhand) of NH-2, India
OVERVIEW
Project Description: | Four laning including strengthening of existing two lane pavement from Barwa Adda to Barakar in the State of Bihar (Jharkhand) of NH-2, India |
Client name: | National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Symonds Travers Morgan |
Contract value in INR Millions / US$ Mill: | 1339.15 / 37.48 |
Completion value INR Millions / US$ Mill: | 1930.00 / 40.28 |
Contract Commencement Date: | 13-Dec-96 |
Contract Completion Date: | 12-Jun-00 |
Revised/Expected Completion Date: | 22-Dec-01 |
Name of the Contractor: | BSC – RBM – PATI Joint Venture |
JV Partners: | B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd |
Share in the Joint Venture: | 50% – 25% – 25% |
Key Items in the Contract: | Earthworks - 16,54,045 m3 GSB - 2,77,115 m3 WMM - 1,90,295 m3 Prime Coat - 4,73,527 m2 Tack Coat - 13,33,860 m2 BM - 26,582 m3 DBM - 1,20,181 m3 BC - 15,387 m3 Cement Concrete Kerb - 91,599 m3 |
Bridge Details | Major / Minor Bridges - 1 Drains - 11,725 m3 Bored Cast-in-situ piles - 653.40 Lm |
DEVELOPMENT OF ROAD
Four laning including strengthening of existing two lane pavement from Raniganj to Panagarh in the State of West Bengal of NH-2, India
OVERVIEW
Project Description: | Four laning including strengthening of existing two lane pavement from Raniganj to Panagarh in the State of West Bengal of NH-2, India |
Client name: | National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi. |
Consultant's Name: | Symonds Travers Morgan |
Contract value in INR Millions / US$ Mill: | 1607.91 / 44.82 |
Completion value INR Millions / US$ Mill: | 2110.00 / 43.88 |
Contract Commencement Date: | 4-Jul-97 |
Contract Completion Date: | 3-Jan-01 |
Revised/Expected Completion Date: | 30-Nov-01 |
Name of the Contractor: | BSC – RBM – PATI Joint Venture |
JV Partners: | B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd |
Share in the Joint Venture: | 50% – 25% – 25% |
Key Items in the Contract: | Earthworks - 14,14,452 m3 GSB - 2,44,915 m3 WMM - 2,02,940 m3 Prime Coat - 99,39,494 m3 Tack Coat - 89,93,904 m3 BM - 21,439 m3 DBM - 1,21,776 m3 BC - 28,761 m3 Cement Concrete Kerb - 95,893 m3 |
Bridge Details | ROB / RUB - 2 Flyover - 1 Major / Minor Bridges - 3 / 7 Slab / Pipe Culvets - 83 / 34 Drains - 11,725 m3 Bored Cast-in-situ piles - 1679 Lm |
DEVELOPMENT OF ROAD
Four laning and strengthening of existing two lanes from Gurgaon in Haryana (Km.36.635) to Kotputli in Rajasthan (Km.162.500) of NH-8, India
OVERVIEW
Project Description: | Four laning and strengthening of existing two lanes from Gurgaon in Haryana (Km.36.635) to Kotputli in Rajasthan (Km.162.500) of NH-8, India |
Client name: | National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi |
Consultant's Name: | SMEC |
Contract value in INR Millions / US$ Mill: | 2646.56 / 74.12 |
Completion value INR Millions / US$ Mill: | 3408.05 / 72.94 |
Contract Commencement Date: | 2-Sep-97 |
Contract Completion Date: | 2-Mar-01 |
Revised/Expected Completion Date: | 20-Mar-01 |
Name of the Contractor: | BSC – RBM – PATI Joint Venture |
JV Partners: | B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd. |
Share in the Joint Venture: | 50% – 25% – 25% |
Key Items in the Contract: | Earthworks - 25,09,532 m3 GSB - 6,22,373 m3 WMM - 5,67,104 m3 Prime Coat - 12,89,510 m2 Tack Coat - 9,00,046 m2 DBM + PCC - 3,67,725 m3 BC - 98,501 m3 Cement Concrete Kerb - 2,64,710 Lm |
Bridge Details | Drains - 35,855 m3 Bored Cast-in-situ piles - 653.40 Lm |
DEVELOPMENT OF ROAD
Improvements to Ankola-Hubli Road (SH-42) Reach S-7 from Km.75/0 to 132/480
OVERVIEW
Project Description: | Improvements to Ankola-Hubli Road (SH-42) Reach S-7 from Km.75/0 to 132/480 |
Client name: | Chief Engineer, PWD, Karnataka. |
Consultant's Name: | RITES with AHRC Division, Yellapur |
Contract value in INR Millions / US$ Mill: | 201.21 |
Completion value INR Millions / US$ Mill: | 283.24 / 7.75 |
Contract Commencement Date: | 1-Jan-92 |
Contract Completion Date: | 11-Dec-95 |
Revised/Expected Completion Date: | 20-Feb-96 |
Name of the Contractor: | Progressive Constructions – Seenaiah & Co. J.V. |
JV Partners: | Progressive Constructions Ltd. – B.Seenaiah & Co. |
Share in the Joint Venture: | 50% – 50% |
Key Items in the Contract: | Earthworks - 3,64,355 m3 WBM Gr.I, II & III - 57,990 m3 Bituminous Macadam - 12,533 m3 Dense Bituminous Macadam - 40,339 m3 Single Coat Surface Dressing - 1,13,870 m2 Tack / Prime Coat - 13,35,220 m2 |
Bridge Details | Minor Bridges - 3 Slab / Pipe Culvets - 102 / 12 Temporary Diversion Roads - 2 kms Vertical Improvements/Restructuring - 3.255 kms |
DEVELOPMENT OF ROAD
Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0
OVERVIEW
Project Description: | Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0 |
Client name: | Chief Engineer, Roads-II, PWD, Jaipur, Rajasthan, India. |
Consultant's Name: | SMEC-ICT, Austrialia |
Contract value in INR Millions / US$ Mill: | 442.1 |
Completion value INR Millions / US$ Mill: | 782.90 / 22.30 |
Contract Commencement Date: | 21-Dec-1991 |
Contract Completion Date: | 30-Nov-1995 |
Revised/Expected Completion Date: | 31-May-96 |
Name of the Contractor: | Progressive Constructions – Seenaiah & Co. J.V. |
JV Partners: | Progressive Constructions Ltd. – B.Seenaiah & Co. |
Key Items in the Contract: | Earthworks - 27,67,169 m3 WBM Gr.I, II & III - 61,733.90 m3 Bituminous Macadam - 1,18,009 m3 Lean Bituminous Macadam - 78,121 m3 Dense Bituminous Macadam - 18,331 m3 Single Coat Surface Dressing - 1,65,977 m2 Tack / Prime Coat - 50,13,529 m2 |
Bridge Details | Major / Minor Bridges - 1 / 19 Slab / Pipe Culvets - 84 / 26 Bypass at Nasirabad - 10.585 kms Inter Sections / Junctions - 31 Temporary Diversion Roads - 2 kms Vertical Improvements/Restructuring - 3.255 kms Horizontal Curves / Realignments - 15 |