OnGoing Projects

Two-laning of Muzaffarpur

Sonbarsa Section of NH -77 (from km 2.8 to km 89.00 ) in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis

OVERVIEW

Project Description: Two-laning of Muzaffarpur – Sonbarsa Section of NH -77 (from km 2.8 to km 89.00 ) in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis
Original Contract value in INR Millions: 5700.00
Original Contract value in US$ Millions: 122.08
Work Completed (%): 0%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 0.00
Amount of work sub-contracted: NIL
* The project was awarded to M/s.BSC-C&C JV. Our Share in the Joint Venture is 50%

Mokama-Munger Highway

Two laning with paved shoulders of Mokama Munger section of NH-80 from km 1.430 to km 70.00 in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis

OVERVIEW

Project Description: Two laning with paved shoulders of Mokama Munger section of NH-80 from km 1.430 to km 70.00 in the State of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis
Client name: Mokama Munger Highway Limited
Original Contract value in INR Millions: 3900.00
Original Contract value in US$ Millions: 84.78
Work Completed (%): 0.00
Certified amount – Actual work done Amount (Rs. Millions) as on date: 0%
Amount of work sub-contracted: NIL
* The project was awarded to M/s.BSC-C&C JV. Our Share in the Joint Venture is 50%

Four laning of Devihalli-Hassan

Deveihalli-Hassan section from Km.110.000 to km.189.500 of NH-48 including a new 2-lane

OVERVIEW

Project Description: Four laning of Deveihalli-Hassan section from Km.110.000 to km.189.500 of NH-48 including a new 2-lane with paved shoulders bypass for channarayapatna town and widening of existing Hassan bypass to 2-lane with paved shoulders on DBFOT basis in the state of Karnataka under NHDP phase III A
Client name: Larsen & Turbo Limited
Original Contract value in INR Millions: 3429.20
Original Contract value in US$ Millions: 74.14
Work Completed (%): 0%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 0.00
Amount of work sub-contracted: NIL
* The work was awarded to M/s.Larsen & Toubro Limited. We are 100% EPC contractor for the project.

Four laning of Godhra to Gujarat

Border Section of NH 59 from Km 129.300 to Km 215.900

OVERVIEW

Project Description: Four laning of Godhra to Gujarat/Madhya Pradesh Border Section of NH 59 from Km 129.300 to Km 215.900 in the State of Gujarat on Design Build, Finance, Operate and Transfer (DBFOT) under NHDP III Project
Client name: BSCPL Godhra Tollways Limited
Original Contract value in INR Millions: 6550.00
Original Contract value in US$ Millions: 140.41
Work Completed (%): 0%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 0.00
Amount of work sub-contracted: NIL
* The project was awrded to M/s.BSCPL Infrastructure Limited

Six laning of Chilkaluripet

Nellore section of NH-5 from km 1182.802 to km 1366.547(approx. length- 183.620 km)

OVERVIEW

Project Description: Six laning of Chilkaluripet – Nellore section of NH-5 from km 1182.802 to km 1366.547(approx. length- 183.620 km) in the State of Andhra Pradesh under NHDP Phase V to be executed as BOT (Toll) project on DBFOT Pattern
Client name: Simhapuri Expressway Limited
Original Contract value in INR Millions: 21500.00
Original Contract value in US$ Millions: 467.39
Work Completed (%): 0%
Certified amount – Actual workdone Amount (Rs. Millions) as on date: 0.00
Amount of work sub-contracted: NIL
* The project was awarded to M/s.KMC-BSCPL JV. Our Share in the Consortium is 50%

DEVELOPMENT OF ROAD ​

Kursela-Pothia-Falka-Meergunj-Sarsi-Kalabalua-Ranigunj-Shaifgunj-Forbesgunj

OVERVIEW

Project Description: Development of Road Kursela-Pothia-Falka-Meergunj-Sarsi-Kalabalua-Ranigunj-Shaifgunj-Forbesganj – Pkg.9
Client name: Road Construction Department, Govt. of Bihar
Original Contract value in INR Millions: 2779.26
Original Contract value in US$ Millions: 55.06
Contract Commencement Date:02-Jan-08
Contract Completion Date: 31-Jan-11
Work Completed (%) 53%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 1579.54
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Araria-Ranigunj-Jarhia-Trivenigunj-Pipra-Supaul-Bishunpur-Bhaptiyahi

OVERVIEW

Project Description: Development of Road Araria-Ranigunj-Jarhia-Trivenigunj-Pipra-Supaul-Bishunpur-Bhaptiyahi – Pkg.8
Client name: Road Construction Department, Govt. of Bihar
Original Contract value in INR Millions: 2997.55
Original Contract value in US$ Millions: 59.39
Contract Commencement Date:03-Jun-09
Contract Completion Date: 31-Jul-11
Work Completed (%) 48%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 1452.55
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Construction of Afghan Parliament and Indian Chancery Buildings at Kabul, Afghanisthan

OVERVIEW

Project Description: Construction of Afghan Parliament and Indian Chancery Buildings at Kabul, Afghanisthan
Client name: Central Public Works Department, Govt. of India.
Original Contract value in INR Millions: 6220.26
Original Contract value in US$ Millions: 126.94
Contract Commencement Date:25-Jan-09
Contract Completion Date: 31-Jan-12
Revised/Expected Completion Date: 31-Jan-12
Work Completed (%) 18%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 1132.75
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Construction of the Ghazni- Gardez and Gardez – Khost Roads in Afghanistan.

OVERVIEW

Project Description: Construction of the Ghazni- Gardez and Gardez – Khost Roads in Afghanistan.
Client name: The Louis Berger Group – Black and Veatch JV Afghanistan.
Original Contract value in INR Millions: 4212.04
Original Contract value in US$ Millions: 85.96
Contract Commencement Date:20-Apr-08
Contract Completion Date: 31-Dec-10
Work Completed (%) 49.05%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 2065.85
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Construction of New Four Lane Roads (Road Nos.2,7,9A,10 &11) in Naya Raipur Development Area in the State of Chhattisgarh

OVERVIEW

Project Description: Construction of New Four Lane Roads (Road Nos.2,7,9A,10 &11) in Naya Raipur Development Area in the State of Chhattisgarh.
Client name: Naya Raipur Development Authority, Govt. of Chhattisgarh.
Consultant's name: M/s.Sheladia Associates Inc in association with Vax Consultants Pvt. Ltd.
Original Contract value in INR Millions: 1449.69
Original Contract value in US$ Millions: 36.87
Contract Commencement Date:02-Jan-08
Contract Completion Date: 31-Oct-10
Work Completed (%) 83.39%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 1208.93
Amount of work sub-contracted: NIL
*The project was awarded to M/s.B.Seenaiah & Company (Projects) Limited

DEVELOPMENT OF ROAD ​

Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.37.75 to Km 0.00 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-9.

OVERVIEW

Project Description: Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.37.75 to Km 0.00 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-9.
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Scott Wilson India (P) Ltd., Rajkumar Ganj, Darbhanga, 846 004 (Bihar).
Original Contract value in INR Millions: 3230.02
Original Contract value in US$ Millions: 71.36
Contract Commencement Date:28-Jan-06
Contract Completion Date: 31-Dec-10
Revised/Expected Completion Date: 31-Dec-10
Work Completed (%) 98.47%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 3180.59
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.69.80 to Km 37.75 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-8.

OVERVIEW

Project Description: Widening and strengthening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from km.69.80 to Km 37.75 in the State of Bihar on East West Corrider under NHDP, Phase-II, Package No.C-II/BR-8.
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Scott Wilson India (P) Ltd., Rajkumar Ganj, Darbhanga, 846 004 (Bihar).
Original Contract value in INR Millions: 3603.00
Original Contract value in US$ Millions: 79.60
Contract Commencement Date:28-Jan-06
Contract Completion Date: 31-Dec-10
Revised/Expected Completion Date: 31-Dec-10
Work Completed (%) 96.27%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 3468.55
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Widening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from Km.155.00 (Kosi Western Ring Bund) to Km.110.00 (Jhanjharpur) in the State of Bihar on Eats West Corridor under NHDP-Phase-II, Project No.C-II/BR-6

OVERVIEW

Project Description: Widening to 4-lane of existing single / intermediate lane carriageway of National Highway No.57 section from Km.155.00 (Kosi Western Ring Bund) to Km.110.00 (Jhanjharpur) in the State of Bihar on East West Corridor under NHDP-Phase-II, Project No.C-II/BR-6
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Wilbur Smith Associates Pvt. Ltd., 75, 14th Cross 2nd Floor, 1st Block, RT Nagar, Bangalore, Karnataka.
Original Contract value in INR Millions: 3834.23
Original Contract value in US$ Millions: 87.17
Contract Commencement Date:28-Jan-06
Contract Completion Date: 30-Nov-10
Revised/Expected Completion Date: 30-Nov-10
Work Completed (%) 93.39%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 3580.78
Amount of work sub-contracted: NIL
*The project was awarded to M/s.BSC-C&C JV. Our Share in the JV is 50%

DEVELOPMENT OF ROAD ​

Lucknow Muzaffar National Highway Project on NH-28 – Package No.LMNHP-EW-II-WB-6

OVERVIEW

Project Description: Lucknow Muzaffar National Highway Project on NH-28 – Package No.LMNHP-EW-II-WB-6
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: ROUGHTON INTERNATIONAL JV CES GROUP, C-188/63, Kasya Road, Padleyganj, Gorakhpur – 273 009, Uttar Pradesh.
Original Contract value in INR Millions: 2743.81
Original Contract value in US$ Millions: 62.97
Contract Commencement Date:24-Oct-05
Contract Completion Date: 31-Oct-10
Revised/Expected Completion Date: 31-Oct-10
Work Completed (%) 89.37%
Certified amount - Actual workdone Amount (Rs. Millions) as on date: 2452.20
Amount of work sub-contracted: NIL
*The project was awarded to M/s.B.Seenaiah & Company (Projects) Limited

Completed Projects

DEVELOPMENT OF ROAD ​

Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0

OVERVIEW

Project Description: Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0
Length of the Road: 186 Kms
Client name: Chief Engineer, Roads-II, PWD, Jaipur, Rajasthan, India
Consultant's Name: SMEC-ICT, Austrialia
Contract value in INR Millions / US$ Mill: 442.1
Completion value in INR Millions / US$ Mill: 782.90 / 22.30
Contract Commencement Date:21-Dec-1991
Contract Completion Date: 30-Nov-1995
Revised/Expected Completion Date: 31-May-96
Name of the Contractor: Progressive Constructions – Seenaiah & Co. J.V.
JV Partners: Progressive Constructions Ltd. – B.Seenaiah & Co.
Share in the Joint Venture: 50% – 50%
Share in the Joint Venture: Earthworks - 27,67,169 m3
WBM Gr.I, II & III - 61,733.90 m3
Bituminous Macadam - 1,18,009 m3
Lean Bituminous Macadam - 78,121 m3
Dense Bituminous Macadam - 18,331 m3
Single Coat Surface Dressing - 1,65,977 m2
Tack / Prime Coat - 50,13,529 m2
Bridge Details Major / Minor Bridges - 1 / 19
Slab / Pipe Culvets - 84 / 26
Bypass at Nasirabad - 10.585 kms
Inter Sections / Junctions - 31
Temporary Diversion Roads - 2 kms
Vertical Improvements/Restructuring - 3.255 kms
Horizontal Curves / Realignments - 15
*The project was awarded to M/s.B.Seenaiah & Company (Projects) Limited

DEVELOPMENT OF ROAD ​

Four Laning of Nagda to Simlada – Dosi / Sejawata from km.25.00 to km. 100.00 on SH-31 Section in the State of Madhya Pradesh

OVERVIEW

Project Description: Four Laning of Nagda to Simlada – Dosi / Sejawata from km.25.00 to km. 100.00 on SH-31 Section in the State of Madhya Pradesh
Client name: Pan India Infrastructures Private Limited.
Contract value in INR Millions / US$ Mill: 3800.00 / 95.05
Completion value in INR Millions / US$ Mill: 3435.50 / 73.52
Contract Commencement Date:01-Apr-08
Contract Completion Date: 30-Dec-09
Name of the Contractor: BSCPL Infrastructure Limited
JV Partners: Progressive Constructions Ltd. – B.Seenaiah & Co.
Share in the Joint Venture: 100%
Key Items in the Contract: Earthwork Excv. & Embankment - 32,23,524 m3
GSB - 4,41,218 m3
WMM - 3,58,263 m3
Prime Coat - 13,27,612 m2
Tack Coat - 14,77,004 m2
DBM - 1,60,127 m3
BC - 55,074 m3
DLC - 1,542 m3
PQC - 2,926 m3
Plain Cement Concrete - 42,184 m3
Reinforced Cement Concrete - 30,132 m3
Reinforcement - 2,808 Mt

DEVELOPMENT OF ROAD ​

Four laning of Jhansi-Lakhnadon section km.255 to km 297 of NH-26 in the state of Madhya Pradesh

OVERVIEW

Project Description: Four laning of Jhansi-Lakhnadon section km.255 to km 297 of NH-26 in the state of Madhya Pradesh
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Contract value in INR Millions / US$ Mill: 1896.30 / 41.35
Completion value in INR Millions / US$ Mill: 2065.90 / 44.48
Contract Commencement Date:27-May-06
Contract Completion Date: 05-Dec-09
Name of the Contractor: BSCPL Infrastructure Limited
Share in the Joint Venture: 100%
Key Items in the Contract: Earthwork Excv. & Embankment - 35,64,850 m3
GSB - 2,53,985 m3
WMM - 2,13,007 m3
Prime Coat - 8,20,189 m2
Tack Coat - 21,49,884 m2
DBM - 62,037 m3
BM - 59,877 m3
BC - 28,075 m3
Mix Seal Surfacing Course - 88,768 m2
Plain Cement Concrete - 35,004 m3
Reinforced Cement Concrete - 33,686 m3
Pile Foundation 1200mm dia - 33,686 m3
Reinforcement - 3937 Mt
Well Foundation - 339 Lm

DEVELOPMENT OF ROAD ​

Widening/modification of roads to create multiple lanes of existing carriageway for high capacity bus system in Delhi – Section: Ambedkar Nagar to Delhi Gate

OVERVIEW

Project Description: Construction works related to widening/modification of roads to create multiple lanes of existing carriageway for high capacity bus system in Delhi – Section: Ambedkar Nagar to Delhi Gate
Client name: Commissioner, Delhi Municipal Corporation, New Delhi.
Contract value in INR Millions / US$ Mill: 1290.78 / 27.93
Completion value in INR Millions / US$ Mill: 1216.48 / 26.29
Contract Commencement Date:05-Sep-06
Contract Completion Date: 26-Nov-09
Name of the Contractor: BSC-C&C Joint Venture
Share in the Joint Venture: 50%
Key Items in the Contract: Earthwork Excv. & Embankment - 30,866 m3
GSB - 21,082 m3
WMM - 15,736 m3
Prime Coat - 61,452 m2
Tack Coat - 7,66,068 m2
DBM - 59,332 m3
BM - 12,220 m3
BC - 14,194 m3
Mastic Asphalt - 1,72,982 m2
PQC - 27,278 m3
DLC - 4,795 m3
Plain Cement Concrete - 8,382 m3
Reinforcement - 415 Mt

DEVELOPMENT OF ROAD ​

Four laning from km.551.00 to km.526.00 of Siliguri to Islampur section of NH-31 in West Bengal

OVERVIEW

Project Description: 4-laning from km.551.00 to km.526.00 of Siliguri to Islampur section of NH-31 in West Bengal
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Contract value in INR Millions / US$ Mill: 1588.94 / 35.83
Completion value in INR Millions / US$ Mill: 2149.41 / 45.28
Contract Commencement Date:05-Apr-06
Contract Completion Date: 05-Apr-06
Name of the Contractor: BSCPL Infrastructure Limited
Share in the Joint Venture: 100%
Key Items in the Contract: Earthwork Excv. & Embankment - 9,37,053 m3
GSB - 1,29,888 m3
WMM - 84,005 m3
Prime Coat - 3,20,729 m2
Tack Coat - 12,27,340 m2
BM - 26,003 m3
DBM - 34,258 m3
BC - 34,258 m3
SDBC - 4,342 m3
PQC - 65,678 m3
DLC - 34,243 m3
Plain Cement Concrete - 35,085 m3
Reinforced Cement Concrete - 28,958 m3
Reinforcement - 3,157 Mt
Pile Foundation 1200mm dia - 240 Lm
Pile Foundation 1200mm dia - 231 Lm

DEVELOPMENT OF ROAD ​

Rehabilitation and Upgradation of Bekaria-Gogunda Section (Km.29.00 to Km.73.00) of NH-76 to 4 lane divided carriageway configuration in the state of Rajasthan on East West Corridors [Contract Package No.EW-II (RJ-2)]

OVERVIEW

Project Description: Rehabilitation and Upgradation of Bekaria-Gogunda Section (Km.29.00 to Km.73.00) of NH-76 to 4 lane divided carriageway configuration in the state of Rajasthan on East West Corridors [Contract Package No.EW-II (RJ-2)]
Client name: National Highways Authority of India, Plot No.G5 & 6, Sector-10, Dwarka, New Delhi.
Contract value in INR Millions / US$ Mill: 4115.00 / 89.47
Completion value in INR Millions / US$ Mill: 4850.50 / 95.62
Contract Commencement Date:6-Nov-05
Contract Completion Date: 28-Feb-07
Name of the Contractor: SOMA – BSCPL JV.
Share in the Joint Venture: 50%
Key Items in the Contract: Earthwork Excv. & Embankment - 101,80,581 m3
GSB - 1,99,554 m3
WMM - 2,03,761 m3
WMM - 7,58,778 m2
Prime Coat - 17,39,820 m2
DBM - 90,954 m3
BC - 31,394 m3
Concrete - 1,97,358 m3
Tunnel Excavation - 1,03,743 m3

DEVELOPMENT OF ROAD ​

Upgrading of Roads from Arcot to Ulundurpettai (Elvanasur), Polur to Chengam, Vriddhachalam to Tiruvarur, Jayankondam to Ariyalur and New Bypass Roads at Chidambaram, Sirkazhi, Arani, Polur, Tiruvannamalai, Tirukkovilur, Vriddhachalam, Ariyalur and Tiruvar

OVERVIEW

Project Description: Upgrading of Roads from Arcot to Ulundurpettai (Elvanasur), Polur to Chengam, Vriddhachalam to Tiruvarur, Jayankondam to Ariyalur and New Bypass Roads at Chidambaram, Sirkazhi, Arani, Polur, Tiruvannamalai, Tirukkovilur, Vriddhachalam, Ariyalur and Tiruvar
Client name: Project Director, Tamil Nadu Road Development Corporation, Chennai
Contract value in INR Millions / US$ Mill: 1689.63 / 37.76
Completion value in INR Millions / US$ Mill: 2082.53 / 46.92
Contract Commencement Date:30-Nov-04
Contract Completion Date: 15-Jun-09
Name of the Contractor: KMC – OSE – BSCPL J.V.
Share in the Joint Venture: 331/3% – 331/3% – 331/3%
Key Items in the Contract: Earthwork Excv. & Embankment - 11,18,354 m3
GSB - 4,75,653 m3
WMM - 2,68,758 m3
Prime Coat - 9,04,300 m2
Tack Coat - 22,45,614 m2
DBM - 1,23,598 m3
BC - 40,297 m3
Plain Cement Concrete - 32,863 m3
Reinforced Cement Concrete - 2,319 m3
Prestressed Concrete - 1,518 m3
Pile Foundation 750mm dia - 1,636 Lm
Pile Foundation 900mm dia - 779 Lm
Open Drains - 10,730 Lm
Saucer Drains - 8,597 Lm
Reinforcement - 621 Mt

DEVELOPMENT OF ROAD ​

Rehabilitation of Taloqan-Kishem Road

OVERVIEW

Project Description: Rehabilitation of Taloqan-Kishem Road
Client name: Ministry of Public Works, Islamic Republic of Afghanisthan, Afghanisthan.
Consultant’s name: SMEC
Contract value in US$ Mill: 22.41
Completion value in US$ Mill: 27.83
Contract Commencement Date:1-Feb-06
Contract Completion Date: 19-Dec-07
Name of the Contractor: BSC-C&C JOINT VENTURE
Share in the Joint Venture: 50% – 50%

DEVELOPMENT OF ROAD ​

Reconstruction of Jalalabad to Asmar Road Km.0+000 to Km.121+500

OVERVIEW

Project Description: Reconstruction of Jalalabad to Asmar Road Km.0+000 to Km.121+500
Client name: United Nations Office for Project Services ( UNOPS) / United States Agency for International Development, Kabul, Afghanistan.
Consultant's Name: Louis Berger Group Inc., USA
Contract value in US$ Mill: 40.65
Completion value in US$ Mill: 39.42
Contract Commencement Date:1-Nov-05
Contract Completion Date: 4-Apr-07
Name of the Contractor: BSC-C&C JOINT VENTURE.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 2,34,909 m3
GSB - 1,49,105 m3
WMM - 1,53,214 m3
Prime Coat - 8,78,891 m2
DBST - 17,57,460 m2
Bridge Details Bridges - 10
Box / Pipe Culvets - 159 / 431
Causeways - 52
Drains - 13521 mtrs

DEVELOPMENT OF ROAD ​

Rehablitation of Economic Facilities & Services REFS Program – Kandahar to Heart Highway Improvement Project – Phase II, Package V – Renovation and Reconstruction Km 456+000 to Km 557+462

OVERVIEW

Project Description: Rehabilitation of Economic Facilities & Services REFS Program – Kandahar to Heart Highway Improvement Project – Phase II, Package V – Renovation and Reconstruction Km 456+000 to Km 557+462
Client name: United States Agency for International Development, Kabul, Afghanistan.
Consultant's Name: Louis Berger Group Inc., USA
Contract value in US$ Mill: 40.96
Completion value in US$ Mill: 51.31
Contract Commencement Date:6-Oct-04
Contract Completion Date: 23-Oct-06
Name of the Contractor: BSC-C&C JOINT VENTURE.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 14,47,424 m3
GSB - 2,76,501 m3
WMM - 1,50,826 m3
BM - 2,72,217 Mt
BC - 79,293 Mt
SBST - 54,469 m2
Milling / Rubblization - 54,469 m2
Bridge Details Major / Minor Bridges - 2 nos 70.50 mtrs & 408.90 mtrs / 8 nos
Slab / Pipe Culvets - 31 / 197

DEVELOPMENT OF ROAD ​

Rehablitation of Economic Facilities & Services REFS Program – Design-Build, Contract for the Rehabilitation of the “Section E” (85 Km stretch from Km.262 to Km.347) of Kabul-Kandahar Highway

OVERVIEW

Project Description: Rehablitation of Economic Facilities & Services REFS Program – Design-Build, Contract for the Rehabilitation of the “Section E” (85 Km stretch from Km.262 to Km.347) of Kabul-Kandahar Highway
Client name: United States Agency for International Development, Kabul, Afghanistan.
Consultant's Name: Louis Berger Group Inc., USAd.
Contract value in US$ Mill: 39.93
Completion value US$ Mill: 44.19
Contract Commencement Date:31-May-03
Contract Completion Date: 26-Jun-05
Name of the Contractor: BSC-C&C JOINT VENTURE.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 14,47,424 m3
GSB - 2,76,501 m3
WMM - 1,50,826 m3
BM - 2,72,217 Mt
BC - 79,293 Mt
SBST - 54,469 m2
Bridge Details Major / Minor Bridges - 16 nos with total length of 768 mts
Slab / Pipe Culvets - 338
Causeways - 3 nos

DEVELOPMENT OF ROAD ​

Design-Build Contract for the Rehabilitation of Kandahar to Spin Boldak Road (Section Km.0+163 to Km.61+440 and from Km.89+771 to Km.90+611)

OVERVIEW

Project Description: Design-Build Contract for the Rehabilitation of Kandahar to Spin Boldak Road (Section Km.0+163 to Km.61+440 and from Km.89+771 to Km.90+611)
Client name: Ministry of Public Works, Islamic Republic of Afghanisthan, Afghanisthan.
Consultant's Name: Sheladia Associates Inc., USA
Contract value in US$ Mill: 24.17
Completion value US$ Mill: 23.34
Contract Commencement Date:15-May-03
Contract Completion Date: 26-Nov-05
Name of the Contractor: BSC-C&C JOINT VENTURE.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 10,96,655 m3
GSB - 1,23,007 m3
WMM - 36,053 m3
Prime Coat - 2,02,390 m2
Tack Coat - 7,37,758 m2
DBM - 23,684 m3
BC - 9,228 m2
Bridge Details Major / Minor Bridges - 3 bridges of 316.65 mts, 190 mts & 280 mtrs
Slab / Pipe Culvets - 136
Drains - 8,099 mts
Causeways - 1,057 mts

DEVELOPMENT OF ROAD ​

Four laning of Satara Kolhapur upto Maharashtra State Border Section of NH-4 Phase – I (Km 592.240 to Km.616.000)

OVERVIEW

Project Description: Four laning of Satara Kolhapur upto Maharashtra State Border Section of NH-4 Phase – I (Km 592.240 to Km.616.000)
Client name: Maharashtra State Road Development Corporation Ltd.
Consultant's Name: CES (India) Pvt. Ltd.
Contract value in US$ Mill: 787.67 / 16.32
Completion value US$ Mill: 889.10 / 19.67
Contract Commencement Date:3-May-02
Contract Completion Date: 31-Dec-05
Revised/Expected Completion Date: 31-Dec-05
Name of the Contractor: BSCPL-SCL JOINT VENTURE.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 10,96,655 m3
GSB - 1,23,007 m3
WMM - 36,053 m3,
Prime Coat - 2,02,390 m2
Tack Coat - 7,37,758 m2
BM - 11,409 m3
DBM + PCC - 23,684 m3
BC - 9,228 m2
Dry Lean Concrete - 26,691 m3
Pavement Quality Concrete - 53,250 m3
Cement Concrete Kerb - 4,186 m3
Bridge Details Major / Minor Bridges - 1 bridge 7 spans of 20.7 mtrs each – length 148 mtrs

DEVELOPMENT OF ROAD ​

Widening & strengthening of existing 2-lane carriageway of NH-60 from Laxmannath (Km.53.410) to Kharagpur (Km.119.275) in state of West Bengal, India

OVERVIEW

Project Description: Widening & strengthening of existing 2-lane carriageway of NH-60 from Laxmannath (Km.53.410) to Kharagpur (Km.119.275) in state of West Bengal, India
Client name: National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Louis Berger International Inc.
Contract value in INR Millions / US$ Mill: 3293.29 / 70.17
Completion value INR Millions / US$ Mill: 3419.94 / 74.68
Contract Commencement Date:30-May-01
Contract Completion Date: 29-Feb-04
Revised/Expected Completion Date: 25-May-06
Name of the Contractor: B.Seenaiah & Company (Projects) Limited.
Key Items in the Contract: Earthworks - 73,39,893 m3
GSB - 3,37,877 m3
WMM - 18,066 m3
Prime Coat - 82,090 m2
Tack Coat - 1,36,345 m2
BC - 2,07,719 m2
Dry Lean Concrete - 1,89769 m3
Pavement Quality Concrete - 1,89769 m3
Bituminous Mastic Course - 1,89769 m3
Bridge Details Flyover - 2
Major / Minor Bridges - 1 / 7
Drains - 11,404 Lm

DEVELOPMENT OF ROAD ​

Widening of existing 2-lanes to 6-lanes divided carriageway facility including rehabilitation of existing 2-lanes from km.273.500 to km.363.885 on Jaipur-Kishangarh section of NH-8 in Rajasthan

OVERVIEW

Project Description: Widening of existing 2-lanes to 6-lanes divided carriageway facility including rehabilitation of existing 2-lanes from km.273.500 to km.363.885 on Jaipur-Kishangarh section of NH-8 in Rajasthan
Client name: GVK Jaipur-Kishangarh Expressway Limited.
Consultant's Name: Lea Associates South Asia Pvt. Ltd.
Contract value in INR Millions / US$ Mill: 2389.80 / 50.12
Completion value INR Millions / US$ Mill: 2389.80 / 54.63
Contract Commencement Date:28-Mar-03
Contract Completion Date: 27-Mar-05
Revised/Expected Completion Date: 27-Mar-05
Name of the Contractor: B.Seenaiah & Company (Projects) Limited.
Key Items in the Contract: Earthworks - 21,92,816 m3
GSB - 3,75,000 m3
WMM - 3,27,430 m3
Prime Coat - 11,54,556 m2
Tack Coat - 43,71,629 m2
BM - 89,973 m3
DBM - 1,33,188 m3
BC - 68,028 m3
Dry Lean Concrete - 17,834 m3
Bridge Details Flyover - 2
Major / Minor Bridges - 1 / 7

DEVELOPMENT OF ROAD ​

Rehabilitation & Upgradation to 4/6 lane divided carriageway for Package KU-IV from Bhilwara Bypass (Km.120/0 of NH-79) to Chittorgarh (Km.183/0 of NH-79) in the State of Rajasthan

OVERVIEW

Project Description: Rehabilitation & Upgradation to 4/6 lane divided carriageway for Package KU-IV from Bhilwara Bypass (Km.120/0 of NH-79) to Chittorgarh (Km.183/0 of NH-79) in the State of Rajasthan
Client name: National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: SNC-Lavalin International Inc.
Contract value in INR Millions / US$ Mill: 1510.40 / 32.03
Completion value INR Millions / US$ Mill: 1774.00 / 38.29
Contract Commencement Date:28-Nov-01
Contract Completion Date: 16-May-04
Revised/Expected Completion Date: 20-Aug-04
Name of the Contractor: B.Seenaiah & Company (Projects) Limited
Key Items in the Contract: Earthworks - 19,38,439 m3
GSB - 2,32,154 m3
WMM - 1,03,373 m3
Prime Coat - 3,85,708 m2
Tack Coat - 11,48,240 m2
Profile Corrective Course - 12,706 m3
DBM - 93,448 m3
BC - 18,073 m3
Dry Lean Concrete - 65,700 m3
Pavement Quality Concrete - 1,24,221 m3
Dry Lean Concrete - 70,534 m3
Bridge Details ROB / RUB - 2 nos RoB (2 spans of 18.536 mts and 2 spans 21.989 mtrs with RCC Girders
Flyover - 2 spans of 18.536 mts and 2 spans of 21.989 mts RCC girders
Major / Minor Bridges - 2 nos 11 spans of 37.0 mtrs each / 11 nos of span 6.60 to 8.80 mtrs
Slab / Pipe Culvets - 38 / 44
Drains - 7,427 m3
Bored Cast-in-situ piles - 653.40 Lm

DEVELOPMENT OF ROAD ​

Four laning including strengthening of existing two lane pavement from Barwa Adda to Barakar in the State of Bihar (Jharkhand) of NH-2, India

OVERVIEW

Project Description: Four laning including strengthening of existing two lane pavement from Barwa Adda to Barakar in the State of Bihar (Jharkhand) of NH-2, India
Client name: National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Symonds Travers Morgan
Contract value in INR Millions / US$ Mill: 1339.15 / 37.48
Completion value INR Millions / US$ Mill: 1930.00 / 40.28
Contract Commencement Date:13-Dec-96
Contract Completion Date: 12-Jun-00
Revised/Expected Completion Date: 22-Dec-01
Name of the Contractor: BSC – RBM – PATI Joint Venture
JV Partners: B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd
Share in the Joint Venture: 50% – 25% – 25%
Key Items in the Contract: Earthworks - 16,54,045 m3
GSB - 2,77,115 m3
WMM - 1,90,295 m3
Prime Coat - 4,73,527 m2
Tack Coat - 13,33,860 m2
BM - 26,582 m3
DBM - 1,20,181 m3
BC - 15,387 m3
Cement Concrete Kerb - 91,599 m3
Bridge Details Major / Minor Bridges - 1
Drains - 11,725 m3
Bored Cast-in-situ piles - 653.40 Lm

DEVELOPMENT OF ROAD ​

Four laning including strengthening of existing two lane pavement from Raniganj to Panagarh in the State of West Bengal of NH-2, India

OVERVIEW

Project Description: Four laning including strengthening of existing two lane pavement from Raniganj to Panagarh in the State of West Bengal of NH-2, India
Client name: National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi.
Consultant's Name: Symonds Travers Morgan
Contract value in INR Millions / US$ Mill: 1607.91 / 44.82
Completion value INR Millions / US$ Mill: 2110.00 / 43.88
Contract Commencement Date:4-Jul-97
Contract Completion Date: 3-Jan-01
Revised/Expected Completion Date: 30-Nov-01
Name of the Contractor: BSC – RBM – PATI Joint Venture
JV Partners: B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd
Share in the Joint Venture: 50% – 25% – 25%
Key Items in the Contract: Earthworks - 14,14,452 m3
GSB - 2,44,915 m3
WMM - 2,02,940 m3
Prime Coat - 99,39,494 m3
Tack Coat - 89,93,904 m3
BM - 21,439 m3
DBM - 1,21,776 m3
BC - 28,761 m3
Cement Concrete Kerb - 95,893 m3
Bridge Details ROB / RUB - 2
Flyover - 1
Major / Minor Bridges - 3 / 7
Slab / Pipe Culvets - 83 / 34
Drains - 11,725 m3
Bored Cast-in-situ piles - 1679 Lm

DEVELOPMENT OF ROAD ​

Four laning and strengthening of existing two lanes from Gurgaon in Haryana (Km.36.635) to Kotputli in Rajasthan (Km.162.500) of NH-8, India

OVERVIEW

Project Description: Four laning and strengthening of existing two lanes from Gurgaon in Haryana (Km.36.635) to Kotputli in Rajasthan (Km.162.500) of NH-8, India
Client name: National Highways Authority of India, Plot No.G-5 & 6, Sector-10, Dwarka, New Delhi
Consultant's Name: SMEC
Contract value in INR Millions / US$ Mill: 2646.56 / 74.12
Completion value INR Millions / US$ Mill: 3408.05 / 72.94
Contract Commencement Date:2-Sep-97
Contract Completion Date: 2-Mar-01
Revised/Expected Completion Date: 20-Mar-01
Name of the Contractor: BSC – RBM – PATI Joint Venture
JV Partners: B.Seenaiah & Co., – Road Builder (M) Sdn Bhd – Pati Sdn Bhd.
Share in the Joint Venture: 50% – 25% – 25%
Key Items in the Contract: Earthworks - 25,09,532 m3
GSB - 6,22,373 m3
WMM - 5,67,104 m3
Prime Coat - 12,89,510 m2
Tack Coat - 9,00,046 m2
DBM + PCC - 3,67,725 m3
BC - 98,501 m3
Cement Concrete Kerb - 2,64,710 Lm
Bridge Details Drains - 35,855 m3
Bored Cast-in-situ piles - 653.40 Lm

DEVELOPMENT OF ROAD ​

Improvements to Ankola-Hubli Road (SH-42) Reach S-7 from Km.75/0 to 132/480

OVERVIEW

Project Description: Improvements to Ankola-Hubli Road (SH-42) Reach S-7 from Km.75/0 to 132/480
Client name: Chief Engineer, PWD, Karnataka.
Consultant's Name: RITES with AHRC Division, Yellapur
Contract value in INR Millions / US$ Mill: 201.21
Completion value INR Millions / US$ Mill: 283.24 / 7.75
Contract Commencement Date:1-Jan-92
Contract Completion Date: 11-Dec-95
Revised/Expected Completion Date: 20-Feb-96
Name of the Contractor: Progressive Constructions – Seenaiah & Co. J.V.
JV Partners: Progressive Constructions Ltd. – B.Seenaiah & Co.
Share in the Joint Venture: 50% – 50%
Key Items in the Contract: Earthworks - 3,64,355 m3
WBM Gr.I, II & III - 57,990 m3
Bituminous Macadam - 12,533 m3
Dense Bituminous Macadam - 40,339 m3
Single Coat Surface Dressing - 1,13,870 m2
Tack / Prime Coat - 13,35,220 m2
Bridge Details Minor Bridges - 3
Slab / Pipe Culvets - 102 / 12
Temporary Diversion Roads - 2 kms
Vertical Improvements/Restructuring - 3.255 kms

DEVELOPMENT OF ROAD ​

Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0

OVERVIEW

Project Description: Widening, Strengthening and reconstruction of Ajmer-Bhilwara-Chittorgarh Road (World Bank Project) from km.1/175 to km.186/0
Client name: Chief Engineer, Roads-II, PWD, Jaipur, Rajasthan, India.
Consultant's Name: SMEC-ICT, Austrialia
Contract value in INR Millions / US$ Mill: 442.1
Completion value INR Millions / US$ Mill: 782.90 / 22.30
Contract Commencement Date:21-Dec-1991
Contract Completion Date: 30-Nov-1995
Revised/Expected Completion Date: 31-May-96
Name of the Contractor: Progressive Constructions – Seenaiah & Co. J.V.
JV Partners: Progressive Constructions Ltd. – B.Seenaiah & Co.
Key Items in the Contract: Earthworks - 27,67,169 m3
WBM Gr.I, II & III - 61,733.90 m3
Bituminous Macadam - 1,18,009 m3
Lean Bituminous Macadam - 78,121 m3
Dense Bituminous Macadam - 18,331 m3
Single Coat Surface Dressing - 1,65,977 m2
Tack / Prime Coat - 50,13,529 m2
Bridge Details Major / Minor Bridges - 1 / 19
Slab / Pipe Culvets - 84 / 26
Bypass at Nasirabad - 10.585 kms
Inter Sections / Junctions - 31
Temporary Diversion Roads - 2 kms
Vertical Improvements/Restructuring - 3.255 kms
Horizontal Curves / Realignments - 15
Scroll to Top